Auditor General Flags MVR 136.5 Million in Unrecoverable Advances Across Cancelled Infrastructure Projects
Politics ·
A compliance audit report released by the Auditor General's Office has flagged numerous issues in the procurement and payment of 634 projects carried out by the Ministry of Infrastructure, Housing and Urban Development between 2019 and 2023, on which a total of MVR 23.06 billion was spent.
Among the matters flagged in the report, released today, are issues in the procurement and payment of the MVR 59.35 million project to install 20 automatic parking systems in Malé and Hulhumalé, and the failure to work towards recovering funds that should be obtained in accordance with state finance regulations.
The report also states that records relating to some expenses were lost in a fire incident in 2024, and that information on the assets recorded in that incident has not been reconciled in the public accounting system.
The audit examined whether state finance regulations were followed in selecting contractors, whether payments were made in accordance with established procedures, whether expenditure was incurred in accordance with the approved budget, and whether funds given as advance for cancelled contracts had been recovered.
Among the projects carried out during the five years of the previous government, the report flagged that of the total MVR 180.2 million given as advance funds to 25 projects cancelled for various reasons by the extended deadline of July 2026, a total of MVR 136.5 million is not recoverable — 76 percent of the funds that should be obtained.
The report said that although the ministry sent letters to some contractors to recover advances for projects whose agreements had been cancelled, the steps specified in state finance regulations were not taken within the required period. It said that where funds were not received within the set payment period, and after a written reminder within seven days and a further seven days' extension, the matter had not been submitted to the courts to recover the funds.
Details of the 25 cancelled projects are flagged in the report. One is the 400 housing units project in Kulhudhuffushi City: MVR 65.99 million was given as advance, and 90 percent of that money has not been recovered. When the contract was cancelled, 18.74 percent of the work had been completed. On 26 August last month, the current government handed the project over to the Housing Development Corporation (HDC).
Among the cancelled projects, 14 were carried out by handing them over to FENAKA Corporation. A total of MVR 63 million was given as advance for those projects, and the audit flagged that MVR 51.8 million has not been recovered. Those projects did not progress sufficiently, and the work of the 14 projects is now being carried out after being handed over to Malé Water and Sewerage Company (MWSC).
The report flagged that because some contractors did not carry out work sufficiently, the state had to spend an additional MVR 112.33 million to hand those projects to other parties and carry them out. It also flagged that many projects were not completed within the period specified in the two-party agreements.
Having disclosed all those issues together with the details of the finances, including the details of the funds, the Audit Office has provided recommendations to rectify those matters.